CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 17, 2021
In general terms and technical analysis, the construction of a house for Manuel has reached 85% which is a very significant achievement in the past few days. The rest of the work that is being and will continue to be done at this time is plastering the walls of the house, then installing doors and windows which only takes about 2 working days at most. And this work will also be carried out after the plastering of the walls is being done at this time.
For work at the final stage, the workers only do the installation of electrical installations and wall painting as well as the final finishing of the work that is classified as refinement. Therefore, the rest of the work that is not yet 100% perfect, which is only four items, from here based on a construction engineering analysis I conclude that a house for Manuel in Venezuela has progressed at 85%.
For clarity, I will present several documents in the form of photos sent by the World Smile Project team in Venezuela as below:
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Back and Right View | |
Back and Left View | |
Back View |
Project Name | Housing Project |
---|---|
Beneficiary | Manuel and Family |
Address | Venezuela |
Important notes in this development are as follows:
- I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
- Financial Update will be done by @mariana4ve
- I will analyze the progress of this construction progress before I publish it and according to technical regulations.
- Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
- Update construction at least once a week
This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.
Previous progress post link
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 16, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 12, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 06, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 01, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 28, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 23, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 17, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - AUGUST 28, 2021
Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil
Great, the construction of Manuel's House is almost complete. Only 15% left. Next week will probably be finished. Good Job.
I think it will be resolved soon
Me encanta el progreso de este proyecto tan maravilloso.
Of course thanks to the hard work of the Venezuelan team, thank you
Gracias a ti.
Ur welcome
Semoga segera bisa di tempati
Aamiin
#club5050 😀
With #club5050 going on without us realizing the process of developing an account is very fast. Thank you for supporting #club5050.
regards @akmal1
Thanks a lot
#club5050
Wellcome bro
😅
Mampu... Nyan payah takheun
Tanyoe mantong minnow
😁
Great build, beautiful house 😍
Thanks
Luar biasa pembangunan tersebut hampir semua selesai.
#club5050
#worldsmileproject50pc