CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 23, 2021

in STEEM FOR BETTERLIFE3 years ago (edited)
Note : 50% of Rewards Donated @worldsmile To Accelerate the Construction of Free Educational Facilities

poster_2021-09-23-035417.png

Of the 12 main activities carried out on the construction of a house for Manuel in Venezuela, 4 of them are being carried out by workers namely embankment which has a weight of 70%, foundation work of 70%, 80 columns or pillars, and 20% beams.

Where this percentage estimate refers to technical analysis, namely the rest of the embankment work will be carried out after making the sloof, foundation work will be completed after the start of embankment and sloof work, column work will be completed when welding ordinary iron joints as wall fasteners, while beam work will be completed when wall installation and the roof is done.

This is the progress analysis of the construction of a house for Manuel that I can present, and for more details on each work carried out, you can see as shown in the table below.

NumberType of workProgress
1Hoarded land70%
2Foundation70%
3Sloof0%
4Columns80%
5Beams20%
6Floor0%
7Wall0%
8Doors and Windows0%
9Roof0%
10Ceiling0%
11Electrical0%
12Painting0%
ProgressCurrent Average20%

For more clarity, let's look at the table that I share below.

CONSTRUCTION PROGRESS UPDATES
PerspectivePresent Condiition
Front and Right ViewIMG_20210923_133551_969.jpg
Front and Left ViewIMG_20210923_133356_967.jpg
Back and Right ViewIMG_20210923_133614_643.jpg
Back and Left ViewIMG_20210923_133559_498.jpg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameHousing Project
BeneficiaryManuel and Family
AddressVenezuela

Important notes in this development are as follows:

  • I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
  • Financial Update will be done by @mariana4ve
  • I will analyze the progress of this construction progress before I publish it and according to technical regulations.
  • Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
  • Update construction at least once a week

This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.


Previous progress post link


Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

Semoga cepat selesai ya pembangunanya. Good report.👍

 3 years ago 

Aamiin

 3 years ago 

Extraordinario amigo, eres un gran aliado para mejorar la claridad del programa.

 3 years ago 

I am very happy in this program, and I will try my best for manuel house and other programs under world smile project

Coin Marketplace

STEEM 0.17
TRX 0.15
JST 0.028
BTC 61651.16
ETH 2369.36
USDT 1.00
SBD 2.50