CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 17, 2021

in STEEM FOR BETTERLIFE3 years ago (edited)
Note : 50% of Rewards Donated To Charity Account : 50% @worldsmile

poster_2021-09-17-055724.png

Of the 12 core activities in the construction of a house for Manuel that has been carried out well, namely filling and foundation, on average this development has achieved 10% progress in the field. However, all kinds of materials needed are already available in different locations and are being worked on such as solid column iron and solid beam iron. The percentage of this calculation refers to the construction site that has been done, While the calculation of the percentage of jobs in different locations is not calculated.

The remaining 70% of the subgrade will be backfilled when the building sloof has been completed, and for the foundation using anchors the remainder will be calculated when the work is complete or when the 20 cm casting is completed. Below is a table of work to be done with the average percentage calculated according to construction engineering analysis

NumberType of workProgress
1Heap70%
2Foundation50%
3Sloof0%
4Columns0%
5Beams0%
6Floor0%
7Wall0%
8Doors and Windows0%
9Roof0%
10Plafond0%
11Electrical0%
12Painting0%
ProgressCurrent Average10%

For more clarity, let's look at the table that I share below.

CONSTRUCTION PROGRESS UPDATES (BEFORE WORK OR 10%)
PerspectiveShop DrawingPresent Condiition
Front and Right Side View2-removebg-preview.pngIMG_20210917_152225_835.jpg
Front and Left Side View1-removebg-preview.pngIMG_20210917_152219_925.jpg
Back and Right Side View3-removebg-preview.pngIMG_20210917_152229_992.jpg
Back and Left Side View4-removebg-preview.pngIMG_20210917_152235_088.jpg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameHousing Project
BeneficiaryManuel and Family
AddressVenezuela

Important notes in this development are as follows:

  • I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
  • Financial Update will be done by @mariana4ve
  • I will analyze the progress of this construction progress before I publish it and according to technical regulations.
  • Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
  • Update construction at least once a week

This is the first progress update for the construction of a house to Manuel in Venezuela from the World Smile Project.


Previous progress post link


Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

The shape of the construction of the house is good. I hope the construction work goes smoothly and according to plan 🤗

 3 years ago 

Thank you for the moral support

 3 years ago 

With my pleasure and I will also try to participate by sharing rewards to support this program😊

 3 years ago 

thanks sis

 3 years ago 

🤗😊

 3 years ago 

:)

 3 years ago 

Genial informe, gracias por el apoyo en la organización y presentación del programa.

Saludos Cordiales.

 3 years ago 

Yo y el equipo de World Smile Project que estamos aquí siempre lo apoyaremos en la caridad y otros campos.
:)

Sir Can I get the verified label of this community.

¡Mam! dame etiqueta de esta comunidad. Ya trabajo en CRYPTO.KIDS comunidad

 3 years ago (edited)

Jejeje déjame averiguar cuáles son las etiquetas, soy tan nueva como tú no las conozco aún.

@klen.civil, conoces los roles de esta comunidad?

So nice creativity

 3 years ago 

thank you so much

Soy nuevo en esta comunidad. No conozco las reglas. Ya trabajo en CRYPTO.KIDS. pero aquí lo que es Beneficiary Rewards y el próximo voto después de cuántas publicaciones. por favor guía

Coin Marketplace

STEEM 0.32
TRX 0.11
JST 0.034
BTC 66569.64
ETH 3235.92
USDT 1.00
SBD 4.31