CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 01, 2021

in STEEM FOR BETTERLIFE3 years ago (edited)
Note : 50% of Rewards Donated to Charity Account : @worldsmile @adollaraday

poster_2021-10-02-052318.png

Progress increase from before was 17,5% (From 35% to 52,5%)


7 of the 12 main works in the construction of a house for Manuel have been carried out, 5 of the 7 have been completed perfectly with a weight of 100% namely hoarded land, foundation, sloof, columns and roof. Meanwhile, 2 of the 7 incomplete jobs are Beams and floor which each have a net weight of 70% and 60%.

The work of the beams will continue to be accelerated along with the installation of the brick wall and will have a 100% progress when the brick wall has been perfectly bonded to the beams. While the calculation of construction techniques for floor work still has the rest of the finishing work or floor smoothing perfectly. The residual weight of the floor is 40% where this engineering calculation also has an effect because the final compaction of the concrete floor will be perfect for at least 14 days.

The next work that will be carried out on Monday will be the two remaining works that coincide with the installation of brick walls and installation of door and window frames. To note, brick wall installation is one of the jobs that has the greatest weight among other jobs. Where later the installation of a brick wall will cover the entire building and the bathroom in the building, besides that the kitchen set will also be counted in this progress.

The following is a table of the average construction progress of the construction of a house for Manuel in Venezuela.

NumberType of workProgress
1Hoarded land100%
2Foundation100%
3Sloof100%
4Columns100%
5Beams70%
6Floor60%
7Wall0%
8Doors and Windows0%
9Roof100%
10Water Installation0%
11Electrical0%
12Painting0%
ProgressCurrent Average52,5%

For more clarity, let's look at the table that I share below.

CONSTRUCTION PROGRESS UPDATES
PerspectivePresent Condiition
Front2VZXybTSZJq1AreaDn1D7Jp7ZEvgLC9TvJctofX1ChMgSZohHGEaBYytw5A9pLi5WC7EP5sk5WsTPK8P3FcnQpWDUtDE45hNBrZeHPJHpMh5c5o28VdbYvw971hUY1daeTQt9XLtCarLLqd6pT7gCp6Hosk.jpeg
Front and Right ViewgPCasciUWmEwHnsXKML7xF4NE4zxEVyvENsPKp9LmDaFv4GuguADaPCZcMmvqygzU3toSGGAmzL69R1AzRtNRAe63LyasuAg8T8AKwW3kdJ7Js54G9iV9yyjV8Nfqga8PQwzUa4KNUG19oVPCJ.jpeg
Front and Left ViewgPCasciUWmEwHnsXKML7xF4NE4zxEVyvENsPKp9LmDaFuzEVTmKBPn9JZDVtyc44s5whUupxkhuUrx7SFwoZxCSHnG731vTmQjrS1LuXW5XMwtHX9W18ExmXi1Efehw65aQQZJjExfod18o9MY.jpeg
Back and Right ViewgPCasciUWmEwHnsXKML7xF4NE4zxEVyvENsPKp9LmDaFuzENe7SypjTm6o764Aatt4gLha9QGWR39pm5C6WfFFP6dLTBpo6CuSodwzErRy7c1QR9tB5a35rFx9wKzpsgSLEwingPNS5SHssZb4.jpeg
Back and Left View2VZXybTSZJq1AreaDn1D7Jp7ZEvgLC9TvJctofX1ChMgSZyGU8WGSXfQpw7LHNw7ozdvBSuBUJBKsWsARWaCbDNS2LaRstQJhXqHwdURtXH2SQLGhX9xio8La1jD2SCPynZ4ksmQJQWhHJb9FoHX7J8vWir.jpeg
BackgPCasciUWmEwHnsXKML7xF4NE4zxEVyvENsPKp9LmDaFv4sJ4kuLeEDSrRiQ6VcfBgxQav71bqc7Xd1QKS7UvCYzhWwcfSiMrY9L2G2MXJqLYHTr8gn5a5GQq79xAkrWT8C6mKDrhzvribgXtA.jpeg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameHousing Project
BeneficiaryManuel and Family
AddressVenezuela

Important notes in this development are as follows:

  • I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
  • Financial Update will be done by @mariana4ve
  • I will analyze the progress of this construction progress before I publish it and according to technical regulations.
  • Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
  • Update construction at least once a week

This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.


Previous progress post link


Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

Buen trabajo amigo, es maravilloso contar con tu detallada descripción de los avances y me alegra que estés de acuerdo con lo que estamos haciendo 🙌😊

Los informes financieros los estoy publicando desde la cuenta @hive-198626
y estamos dentro del presupuesto y sin contratiempos. 🤜💥🤛

 3 years ago 

Hopefully it will be finished quickly 😇😇😇😇

 3 years ago 

Salam dari pendatang baru bg😊

 3 years ago 

salam juga bg

This post has been featured in the latest edition of Steem News...

Coin Marketplace

STEEM 0.17
TRX 0.16
JST 0.029
BTC 61224.26
ETH 2383.35
USDT 1.00
SBD 2.55