CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 01, 2021
Progress increase from before was 17,5% (From 35% to 52,5%)
7 of the 12 main works in the construction of a house for Manuel have been carried out, 5 of the 7 have been completed perfectly with a weight of 100% namely hoarded land, foundation, sloof, columns and roof. Meanwhile, 2 of the 7 incomplete jobs are Beams and floor which each have a net weight of 70% and 60%.
The work of the beams will continue to be accelerated along with the installation of the brick wall and will have a 100% progress when the brick wall has been perfectly bonded to the beams. While the calculation of construction techniques for floor work still has the rest of the finishing work or floor smoothing perfectly. The residual weight of the floor is 40% where this engineering calculation also has an effect because the final compaction of the concrete floor will be perfect for at least 14 days.
The next work that will be carried out on Monday will be the two remaining works that coincide with the installation of brick walls and installation of door and window frames. To note, brick wall installation is one of the jobs that has the greatest weight among other jobs. Where later the installation of a brick wall will cover the entire building and the bathroom in the building, besides that the kitchen set will also be counted in this progress.
The following is a table of the average construction progress of the construction of a house for Manuel in Venezuela.
Number | Type of work | Progress |
---|---|---|
1 | Hoarded land | 100% |
2 | Foundation | 100% |
3 | Sloof | 100% |
4 | Columns | 100% |
5 | Beams | 70% |
6 | Floor | 60% |
7 | Wall | 0% |
8 | Doors and Windows | 0% |
9 | Roof | 100% |
10 | Water Installation | 0% |
11 | Electrical | 0% |
12 | Painting | 0% |
Progress | Current Average | 52,5% |
For more clarity, let's look at the table that I share below.
Perspective | Present Condiition |
---|---|
Front | |
Front and Right View | |
Front and Left View | |
Back and Right View | |
Back and Left View | |
Back |
Project Name | Housing Project |
---|---|
Beneficiary | Manuel and Family |
Address | Venezuela |
Important notes in this development are as follows:
- I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
- Financial Update will be done by @mariana4ve
- I will analyze the progress of this construction progress before I publish it and according to technical regulations.
- Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
- Update construction at least once a week
This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.
Previous progress post link
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 28, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 23, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 17, 2021
CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - AUGUST 28, 2021
Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil
@tipu curate
Upvoted 👌 (Mana: 3/5) Get profit votes with @tipU :)
Buen trabajo amigo, es maravilloso contar con tu detallada descripción de los avances y me alegra que estés de acuerdo con lo que estamos haciendo 🙌😊
Los informes financieros los estoy publicando desde la cuenta @hive-198626
y estamos dentro del presupuesto y sin contratiempos. 🤜💥🤛
Hopefully it will be finished quickly 😇😇😇😇
Salam dari pendatang baru bg😊
salam juga bg
This post has been featured in the latest edition of Steem News...