CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - SEPTEMBER 28, 2021

in STEEM FOR BETTERLIFE3 years ago
Note : 50% of Rewards Donated to Charity Account : @worldsmile @adollaraday

poster_2021-09-28-095124.png

Progress increase from before was 15% (From 20% to 35%)


Of the 12 main activities carried out on the construction of a house for Manuel in Venezuela, 5 of them are being carried out by workers namely embankment which has a hoarded land of 70%, foundation work of 80%, 100 columns or pillars, 70% beams and 100% roof. Two of the five works being carried out have been 100% completed, while the other three which include hoarder land, foundation and beam are still in the work stage considering that the Hoarded land and foundation will be completed when the sloof and floor work has been completed, while the beams will be completed when installed. wall work and installation of door and window frames is completed or is being worked on later.

The next target of work that will be carried out and will take several working days is the installation of pipes as a substitute for sloof, the rest of the Hoarded land and floor casting. Then the wall work will also be carried out along with the installation of door and window frames. This is the progress analysis of the construction of a house for Manuel that I can present, and for more details on each work carried out, you can see as shown in the table below.

NumberType of workProgress
1Hoarded land70%
2Foundation80%
3Sloof0%
4Columns100%
5Beams70%
6Floor0%
7Wall0%
8Doors and Windows0%
9Roof100%
10Ceiling0%
11Electrical0%
12Painting0%
ProgressCurrent Average35%

For more clarity, let's look at the table that I share below.

CONSTRUCTION PROGRESS UPDATES
PerspectivePresent Condiition
FrontIMG_20210928_203946_916.jpg
Front and Right ViewIMG_20210928_203907_790.jpg
Front and Left ViewIMG_20210928_203901_949.jpg
Back and Right ViewIMG_20210928_204239_286.jpg
Back and Left ViewIMG_20210928_204230_565.jpg
BackIMG_20210928_203950_722.jpg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameHousing Project
BeneficiaryManuel and Family
AddressVenezuela

Important notes in this development are as follows:

  • I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
  • Financial Update will be done by @mariana4ve
  • I will analyze the progress of this construction progress before I publish it and according to technical regulations.
  • Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
  • Update construction at least once a week

This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.


Previous progress post link


Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

Excelente plan para mañana. El piso completo 😎

 3 years ago 

oke, keep up the good work and hopefully it will be over soon

Coin Marketplace

STEEM 0.28
TRX 0.11
JST 0.034
BTC 66137.63
ETH 3161.38
USDT 1.00
SBD 4.13