CONSTRUCTION PROGRESS UPDATES : A HOUSE FOR MANUEL FROM WORLD SMILE PROJECT - OCTOBER 12, 2021

in STEEM FOR BETTERLIFE3 years ago (edited)
Note : 50% of Rewards Donated to Charity Account : @worldsmile @adollaraday

poster_2021-10-12-033434.png


6 Days ago the work of laying bricks as walls has started and was followed by installation of clean water and dirty water. A total of 12 works that have been done perfectly, 7 of which are Hoarded land, Foundation, Sloof, Columns, Beams, Floor, and Roof with each progressing 100%. Meanwhile, the other 2 main works being carried out are wall and waterinstallation, each of which has progress of 60% and 80%.

Where the wall work from bricklaying will be considered complete when the installation of door and window frames has been perfect and the wall must be plastered. The target completion of this wall work will take up to 4 to 5 working days. Meanwhile, the water installation has been carried out in the indoor area when installing pipes for dirty water and clean water. The remainder of this work will be calculated at 100% when the sewerage is completed.

The progress movement for the past 6 days was 10%, at which time the average progress value was still at 60%. And at this time after I did a technical analysis during the work, the average progress determination was 70%.

The following is a table of the average construction progress of the construction of a house for Manuel in Venezuela.

NumberType of workProgress
1Hoarded land100%
2Foundation100%
3Sloof100%
4Columns100%
5Beams100%
6Floor100%
7Wall60%
8Doors and Windows0%
9Roof100%
10Water Installation80%
11Electrical0%
12Painting0%
ProgressCurrent Average70%

For more clarity, let's look at the table that I share below.

CONSTRUCTION PROGRESS UPDATES
PerspectivePresent Condiition
FrontIMG_20211012_114730_915.jpg
Front and Right ViewIMG_20211012_114725_023.jpg
Front and Left ViewIMG_20211012_151041_942.jpg
Back and Right ViewIMG_20211012_114715_267.jpg
Back and Left ViewIMG_20211012_114704_350.jpg
BackIMG_20211012_114710_091.jpg
IndoorIMG_20211012_114822_188.jpg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameHousing Project
BeneficiaryManuel and Family
AddressVenezuela

Important notes in this development are as follows:

  • I will always publish the progress of every progress according to the pictures or videos sent by the Venezuelan team
  • Financial Update will be done by @mariana4ve
  • I will analyze the progress of this construction progress before I publish it and according to technical regulations.
  • Documents in the form of images or videos belong to the Venezuelan team entrusted to me to publish.
  • Update construction at least once a week

This is a technical analysis report regarding the construction progress of the construction of a house for Manuel in Venezuela.


Previous progress post link


Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  

Feliz por su gran aporte y ayuda.☺

 3 years ago 

thanks

 3 years ago 

Sepertinya hampir selesai pembangunan nya. Semoga rumahnya segera bisa di tempati

 3 years ago 

Ya kak hampir selesai

 3 years ago 

Me encanta este proyecto, es un avance muy grande del cual me siento muy orgullosa de que se lleve a cabo.

Cada día que pasa nos acercamos a la meta 😍🚀🌟

 3 years ago 

Of course this happiness will have a sweet ending 🤩

Nice post, I love this #club5050

Coin Marketplace

STEEM 0.26
TRX 0.11
JST 0.033
BTC 64107.21
ETH 3073.84
USDT 1.00
SBD 3.88