WSP : Construction Progress Report from Water System and Public Latrine [January 31, 2022]

in STEEM FOR BETTERLIFE3 years ago
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

image.png

Construction Progress Report from Water System and Public Latrine

Today is January 31, 2022, the construction of the water system and public latrine has now reached 50% progress, which according to the technical analysis of 11 main works and other works have now been completed with 5 work items while 6 of the other items have mostly been being worked on by workers at the construction site. The wall, floor and water tube are now almost completed at the construction site, then the roof of this building which uses mild steel is done separately. So it can be ascertained that these 4 work items are carried out simultaneously by different workers.

For the wall, the finished work item is bricklaying while the plastering is almost done in accordance with the current condition where the back and side areas have been completed and the front area only takes about half a day of work. With regard to wall work which is classified as a skill work for ceramic installation, this item is carried out after the wall plastering is perfect.

For the floor, the work item which is almost finished is the elevation of the embankment which will then be continued with the casting of the floor. So it can be ascertained that after the two work items on the floor are completed, the installation of floor tiles will immediately be carried out. Likewise with the water tub, which is now almost finished, only the ceramics are left for both the floor and the walls of the water tub.

Other work that is done separately is for the roof, this is because the type of roof that we will use is a light steel frame. The process of welding this frame is almost finished by workers in the welding workshop. For more details on each item of construction work for the water system and public lantrine, you can see the work table and photo table of the current condition as below.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnComplete
5.BeamComplete
6.WallAlmost complete
7.FloorAlmost complete
8.Water tubAlmost complete
9.RoofAlmost complete
10.PaintingOn Progress
11.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Back Viewimage.png
Right Viewimage.png
Left Viewimage.png
Back and Right Viewimage.png
Back and Left Viewimage.png

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

This is great, thanks for the update.

 3 years ago 

Thanks

 3 years ago 

Program yang baik semoga lancar terus dalam perjalanan pembuatan bangunannya.

Salam hangat berjuang untuk steem amal.
#club100
😊

 3 years ago 

Terima kasih

 3 years ago 

Nice work sir

 3 years ago 

Thanks

 3 years ago 

You are welcome sir

 3 years ago 

sir i have accepted what you asked me on telegram

 3 years ago 

Geuthat kakarat update

 3 years ago 

🤣😉

 3 years ago 

how are you my dear friend? soon with the help of God they will have a meeting place, the expenses are many but they will soon have to cover all the expenses and the needs of the workers, greetings from Venezuela @klen.civil

d2dd51ac-1bc2-4c6e-b36a-8ef805c3d0cb.jpg

Construyamos Un Mejor Futuro En Steemit.
#affable #twopercent #venezuela Discord josemen#9810

 3 years ago 

Thanks

 3 years ago 

Great report. Keep it up bro..

 3 years ago 

Thanks sist

 3 years ago 

Anytime brother..

Coin Marketplace

STEEM 0.16
TRX 0.16
JST 0.028
BTC 73442.21
ETH 2602.53
USDT 1.00
SBD 2.39