WSP : Construction Progress Report from Water System and Public Latrine [January 31, 2022]
Today is January 31, 2022, the construction of the water system and public latrine has now reached 50% progress, which according to the technical analysis of 11 main works and other works have now been completed with 5 work items while 6 of the other items have mostly been being worked on by workers at the construction site. The wall, floor and water tube are now almost completed at the construction site, then the roof of this building which uses mild steel is done separately. So it can be ascertained that these 4 work items are carried out simultaneously by different workers.
For the wall, the finished work item is bricklaying while the plastering is almost done in accordance with the current condition where the back and side areas have been completed and the front area only takes about half a day of work. With regard to wall work which is classified as a skill work for ceramic installation, this item is carried out after the wall plastering is perfect.
For the floor, the work item which is almost finished is the elevation of the embankment which will then be continued with the casting of the floor. So it can be ascertained that after the two work items on the floor are completed, the installation of floor tiles will immediately be carried out. Likewise with the water tub, which is now almost finished, only the ceramics are left for both the floor and the walls of the water tub.
Other work that is done separately is for the roof, this is because the type of roof that we will use is a light steel frame. The process of welding this frame is almost finished by workers in the welding workshop. For more details on each item of construction work for the water system and public lantrine, you can see the work table and photo table of the current condition as below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Complete |
5. | Beam | Complete |
6. | Wall | Almost complete |
7. | Floor | Almost complete |
8. | Water tub | Almost complete |
9. | Roof | Almost complete |
10. | Painting | On Progress |
11. | Electrical | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Back View | |
Right View | |
Left View | |
Back and Right View | |
Back and Left View |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [January 29, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 25, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 22, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien
Thanks
@klen.civil
This is great, thanks for the update.
Thanks
Program yang baik semoga lancar terus dalam perjalanan pembuatan bangunannya.
Salam hangat berjuang untuk steem amal.
#club100
😊
Terima kasih
Nice work sir
Thanks
You are welcome sir
sir i have accepted what you asked me on telegram
Geuthat kakarat update
🤣😉
Thanks
@tipu curate 2
Excelente trabajo amigo
Upvoted 👌 (Mana: 0/5) Get profit votes with @tipU :)
Great report. Keep it up bro..
Thanks sist
Anytime brother..