WSP : Construction Progress Report from Water System and Public Latrine [January 22, 2022]
Today is January 22, 2022, Of the 11 main works on the construction of the Water System and Public Latrine, three works have been completed and two are in progress. Three jobs that have been completed are Bouwplank, Footing and Sloof. While the two works being carried out are Column, Wall and Water tub, where the main column work for all the steel has been installed and the other has been wrapped with formwork which has been filled with concrete.
For the walls of the building that have been installed in the latrine section and are almost finished, the steps to be carried out on the walls are to complete the brickwork and at the same time install pipes on the wall as a place for installing water faucets, while other work that is deemed necessary is a water tub, this work has reached less than half the work.
The three works that are being carried out by these workers will be completed within the next day at the latest, in addition, after this work is completed, the next step is to install the beams, plaster and install wall tiles. The floor work will also be carried out in conjunction with the completion of the water tub in this building.
For analysis of construction techniques from the Water System and Public Latrine per day it has reached 24% this happens because the work items are 11 and can be categorized by separating each work item itself. For more details, you can see as in the table and the current condition of each work on the construction as below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Almost complete |
5. | Wall | Almost complete |
6. | Beam | On Progres |
7. | Floor | On Progress |
8. | Water tub | Almost complete |
9. | Roof | On Progress |
10. | Painting | On Progress |
11. | Electrical | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Left and Right View |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve
Thanks
@klen.civil
Great report.good job
Thanks sist
Anytime..
@klen.civil, te he buscado por Discord y no te consigo. Quisiera saber si tienes grupo para la nueva propuesta de Steemit Blog.
Mi Discord es #0466
You can send a message to my telegram, link is in my bio
Thank you for updating us on the progress.
This post has been featured in the latest edition of Steem News...
Thanks for the information about the progress of the project,
I'm going to write today's article again #worldsmileproject50pc for support. And thank you for giving us the opportunity to do such a charitable thing. 😇🙏🤲
I have included this post in the 31th issue of Steem News Magazine For Steemit Platform | January 22, 2022.
almost on its half way dear... Keep it up...
100.0% уникальности текста (uniqueness of the text)
Здравствуйте. Это полуавтоматическая проверка уникальности сервисом content-watch. Пожалуйста, сообщайте о неточностях. Уникальность вашей статьи согласно сервиса content-watch.ru равна: 100.0%
Hello. This is a half-automatic uniqueness check by the content-watch service Please report any inaccuracies The uniqueness of your stat th according to the content-watch.ru service is equal to: 100.0%