WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
Today is January 15, 2022, The construction of the Water System and Public Latrine which was built from the World Smile Project budget has now experienced an increase since the first progress update four days ago, where the improvement is the completion of the footing or foundation of the building being built.
Apart from this, the reinforcement of each main column in the building has been installed perfectly, and for now the work being carried out is laying bricks on the foundation that serves as a building riser, later on above the brick sloof and floor work will be carried out. The target for completion of building elevation using bricks is one working day.
This is the overall technical analysis of the Water System and Public Latrine building that I calculated with a construction progress of 8%. You can see the conditions in the field in the table and figure below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | On Progress |
4. | Column | Almost complete |
5. | Beam | On Progress |
5. | Wall | On Progress |
7. | Water tub | On Progress |
8. | Roof | On Progress |
9. | Painting | On Progress |
10. | Electrical | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Left and Right View |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve
Thanks
@klen.civil
Wow...great work sir, finally soon a lot of people can use the public latrine and water.
Stay Bless!❤️🙏
Thanks bien
Your welcome sir
Me encanta ver que ya inició la construcción. Éxitos 😁✌️
Thanks mariana4ve
😁
Semoga cepat selesai bang untuk bangunan di mesjid 👏👍
#club5050
#club75