WSP : Construction Progress Report from Water System and Public Latrine [February 08, 2022]

in STEEM FOR BETTERLIFE2 years ago
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

image.png

Construction Progress Report from Water System and Public Latrine

Today is February 08, 2022, the increase in construction progress of the water system and public latrine has reached 75%. This is in accordance with the technical analysis of the work items that have been, are being and have not been carried out by workers. The 11 main work items of this building have mostly been done and in the past few days until today the workers are working on installing wall and floor tiles on the building walls and water tubs.

Another work that is being done separately is the roof of the building, where the roof is made of steel frame. For other types of work that have not been done are painting, electrical installations and water systems. The completion target of the construction of the water system and publick latrine is 10 to 12 working days at the longest. To be clear, you can see the progress of the construction of the water system and public lantrine which has reached 75%, as shown in the table of work items and the photo table of the current condition as below:

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnComplete
5.BeamComplete
6.WallComplete
7.FloorAlmost complete
8.Water TubAlmost complete
9.RoofAlmost complete
10.PaintingOn Progress
11.Electrical and Water SystemOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Right Viewimage.png
Left Viewimage.png
Back Viewimage.png
Back and Right Viewimage.png
Back and Left Viewimage.png
Roof Trussimage.png

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 2 years ago 

This is great progress, and this will create huge impact to the society, thank you for this update.

 2 years ago 

Ur welcome

 2 years ago 

Wow...25% more our brothers and sisters will finally benefits the World Smile Project❤️❤️

 2 years ago 

The target for completion of this project is no later than 12 days, hopefully it will be made easier

 2 years ago 

Wow..that sounds amazing..well! Advance congratulations sir.

 2 years ago 

Thank you so much @bien

 2 years ago 

Your much welcome sir.

 2 years ago 

Mantap. Kontruksi sudah mencapai 75%.
Selamat sudah mencapai Triple Dolphin. Luar Biasa. Bentar lagi lon akan nyusul.... he he he

 2 years ago 

Aamiin, neu power up aju beu jai
hehehe

 2 years ago 

Mantap sekali, beramal lewat steemit

Coin Marketplace

STEEM 0.28
TRX 0.12
JST 0.032
BTC 69947.15
ETH 3908.93
USDT 1.00
SBD 3.71