WSP : Construction Progress Report from Water System and Public Latrine [February 08, 2022]
Today is February 08, 2022, the increase in construction progress of the water system and public latrine has reached 75%. This is in accordance with the technical analysis of the work items that have been, are being and have not been carried out by workers. The 11 main work items of this building have mostly been done and in the past few days until today the workers are working on installing wall and floor tiles on the building walls and water tubs.
Another work that is being done separately is the roof of the building, where the roof is made of steel frame. For other types of work that have not been done are painting, electrical installations and water systems. The completion target of the construction of the water system and publick latrine is 10 to 12 working days at the longest. To be clear, you can see the progress of the construction of the water system and public lantrine which has reached 75%, as shown in the table of work items and the photo table of the current condition as below:
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Complete |
5. | Beam | Complete |
6. | Wall | Complete |
7. | Floor | Almost complete |
8. | Water Tub | Almost complete |
9. | Roof | Almost complete |
10. | Painting | On Progress |
11. | Electrical and Water System | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Back and Left View | |
Roof Truss |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [February 04, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 31, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 29, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 25, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 22, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien
Thanks
@klen.civil
This is great progress, and this will create huge impact to the society, thank you for this update.
Ur welcome
Wow...25% more our brothers and sisters will finally benefits the World Smile Project❤️❤️
The target for completion of this project is no later than 12 days, hopefully it will be made easier
Wow..that sounds amazing..well! Advance congratulations sir.
Thank you so much @bien
Your much welcome sir.
Mantap. Kontruksi sudah mencapai 75%.
Selamat sudah mencapai Triple Dolphin. Luar Biasa. Bentar lagi lon akan nyusul.... he he he
Aamiin, neu power up aju beu jai
hehehe
@tipu curate 2
Good job my friend
Upvoted 👌 (Mana: 4/7) Get profit votes with @tipU :)
Mantap sekali, beramal lewat steemit