WSP : Construction Progress Report from Water System and Public Latrine [February 19, 2022]
Of the many work items for the water system and public latrine on February 19, 2022, this construction has left two work items, namely the installation of a roof on a steel frame and the installation of electric current. The roof work will be carried out in the next two days considering that the order for this roof is outside the province of Aceh, namely North Sumatra. And after the installation of this roof will be continued with the electrical installation. The aggregate percentage of these two work items is 5% for roofing and 3% for electrical installations. So according to the analysis of construction techniques per day the work of the water system and public latrine has reached 92%. For donors and other steemit platform users, you can clearly see the percentage of progress and the current condition of the water system and public latrine construction as below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Complete |
5. | Beam | Complete |
6. | Wall | Complete |
7. | Floor | Complete |
8. | Water Tub | Complete |
9. | Roof | Almost Complete |
10. | Painting | Complete |
11. | Electrical and Water System | Almost Complete |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Right View | |
Left View | |
Back and Right View | |
Back and Left View | |
Water Tub |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien
Thanks
@klen.civil
Semoga proyek worldsmileproject berjalan dengan lancar sampai selesai, semangat terus buat anda bapak😇
Mantap sukses terus:)
Your struggle is really good. I wish you continued success.
Thank you so much
Good to see a nice progress. Thank you for the update and success!