Official Report WSP : Contruction Progress of Free Education Center East Aceh 30% [September 1, 2022]

in STEEM FOR BETTERLIFE2 years ago
image.png

The construction of the free education center for East Aceh, whose funding source is from steem under the auspices of the World Smile Project charity, has now progressed to construction at 30% of the total 10 main work items. Where three main work items have been completed, namely Site Clearing and Landing Altitude Measurement with a weight of 5%, Footing with a weight of 10% and Sloof with a weight of 10%. While one main work item currently being worked on is Post with a weight of 5% out of 15% of the total weight.

Where post work items totaling 11 units have been installed 4 units perfectly today, and this work continues to perfection. The obstacles in the overall work of the free education center are due to the rainy weather that has hit all of Aceh in the last two weeks which has resulted in a slight delay in the work carried out by workers, especially on the current post item. However, we from the WSP team have made various efforts to accelerate development.

To note that all items of this post work will be completed in about 2 to 3 working days if there are no problems, and in accordance with calculations or analysis of construction techniques according to Indonesian state standards, I will report the construction progress of the Free Education Center as of September 1, 2022 is 30% of the total, for more details, see the conditions and conditions of the free education center below.

NoType of WorkPersentase
1.Site Clearing and Landing Altitude Measurement5/5
2.Footing10/10
3.Sloof10/10
4.Round Floor Building0/8
5.Post5/15
6.Wall0/12
7.Beam0/10
8.Steel Truss Roof0/20
9.Painting0/5
10.Finishing0/5
Total Persentase30/100

And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :

Current condition of Free Education Center Development for East Aceh
image.pngimage.png
Front ViewBack View
image.pngimage.png
Right ViewLeft View
image.pngimage.png
Another perspectiveAnother perspective
image.pngimage.png
Another perspectiveAnother perspective
Other documentation is in the form of photos of workers in activity and on site materials
image.pngimage.png
Multiplex for formworkStone for casting
image.pngimage.png
Iron for postIron for post

This is the progress report on the construction of the free education center for East Aceh which has started today as of September 1, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.

East Aceh, September 1, 2022
@klen.civil
WSP Construction Supervisor

Sort:  
 2 years ago 

Thank you for the feedback!
Fingers cross that the rain will not delay the process any further. 🤞

 2 years ago 

I have no doubt that the decisions that are going to be taken to accelerate the development of the work will be the correct ones.

Here in Venezuela the rains have also manifested themselves, in fact we have the presence of "fog" at every sunrise.

 2 years ago 

Of course we will use any means so that this development can be realized soon

Semoga Allah lancarkan

 2 years ago 

Aamin

 2 years ago 

Karap siap
Pajan tapasang atap

 2 years ago 

Preh ile dang leuh geu peuget kolom dan balok atas

This post has been featured in the latest edition of Steem News...

Coin Marketplace

STEEM 0.27
TRX 0.11
JST 0.031
BTC 71178.18
ETH 3871.22
USDT 1.00
SBD 3.50