Official Report WSP : Contruction Progress of Free Education Center East Aceh 30% [September 1, 2022]
The construction of the free education center for East Aceh, whose funding source is from steem under the auspices of the World Smile Project charity, has now progressed to construction at 30% of the total 10 main work items. Where three main work items have been completed, namely Site Clearing and Landing Altitude Measurement with a weight of 5%, Footing with a weight of 10% and Sloof with a weight of 10%. While one main work item currently being worked on is Post with a weight of 5% out of 15% of the total weight.
Where post work items totaling 11 units have been installed 4 units perfectly today, and this work continues to perfection. The obstacles in the overall work of the free education center are due to the rainy weather that has hit all of Aceh in the last two weeks which has resulted in a slight delay in the work carried out by workers, especially on the current post item. However, we from the WSP team have made various efforts to accelerate development.
To note that all items of this post work will be completed in about 2 to 3 working days if there are no problems, and in accordance with calculations or analysis of construction techniques according to Indonesian state standards, I will report the construction progress of the Free Education Center as of September 1, 2022 is 30% of the total, for more details, see the conditions and conditions of the free education center below.
No | Type of Work | Persentase |
---|---|---|
1. | Site Clearing and Landing Altitude Measurement | 5/5 |
2. | Footing | 10/10 |
3. | Sloof | 10/10 |
4. | Round Floor Building | 0/8 |
5. | Post | 5/15 |
6. | Wall | 0/12 |
7. | Beam | 0/10 |
8. | Steel Truss Roof | 0/20 |
9. | Painting | 0/5 |
10. | Finishing | 0/5 |
Total Persentase | 30/100 |
And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :
Front View | Back View |
Right View | Left View |
Another perspective | Another perspective |
Another perspective | Another perspective |
Multiplex for formwork | Stone for casting |
Iron for post | Iron for post |
This is the progress report on the construction of the free education center for East Aceh which has started today as of September 1, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.
Official Report WSP : Contruction Progress of Free Education Center East Aceh 27% [August 26, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 22% [August 20, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 17% [August 16, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 12% [August 11, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 5% [August 5, 2022]
Project | Free Education Center |
---|---|
Type | Buiding Contruction |
Size or Dimention | 9 x 6 meter |
Address | Tanjong Punti village, Madat district, East Aceh |
Benefit recipients | Early Childhood |
Teacher | @steemitcountry |
East Aceh, September 1, 2022
@klen.civil
WSP Construction Supervisor
Thank you for the feedback!
Fingers cross that the rain will not delay the process any further. 🤞
I have no doubt that the decisions that are going to be taken to accelerate the development of the work will be the correct ones.
Here in Venezuela the rains have also manifested themselves, in fact we have the presence of "fog" at every sunrise.
Of course we will use any means so that this development can be realized soon
Semoga Allah lancarkan
Aamin
Karap siap
Pajan tapasang atap
Preh ile dang leuh geu peuget kolom dan balok atas
This post has been featured in the latest edition of Steem News...