Official Report WSP : Contruction Progress of Free Education Center East Aceh 22% [August 20, 2022]
Two of the main work on the construction of the free education center, which was funded by the World Smile Project Int, have been completed with a total percentage of each work item 5% from site clearing and landing altitude measurement and 10% from footing. Apart from the work that has been completed, there are other works which are mandatory work to complete this construction which is currently being done, namely sloof which already has 5% progress from 10% in total, and posts which already have 2% progress from 15% in total. total. Where this sloof work has increased progress significantly because part of the total sloof has been completed and the percentage of posts is only obtained from the binding of the iron that has been installed as a connection to the sloof.
The target completion of this sloof only takes between 1 to 2 working days, while to complete the post work it takes between 4 to 7 working days. It is important to note that post work will be the priority of work after completing the work from the sloof, and then it will be followed by other main work items such as round floor building and wall work. So from all the explanations above and in accordance with the prevailing analysis of Indonesian construction techniques, I report the Construction Progress of Free Education Center East Aceh 22% as of August 20, 2022 and the details can be seen in the table below.
No | Type of Work | Persentase |
---|---|---|
1. | Site Clearing and Landing Altitude Measurement | 5/5 |
2. | Footing | 10/10 |
3. | Sloof | 5/10 |
4. | Round Floor Building | 0/8 |
5. | Post | 2/15 |
6. | Wall | 0/12 |
7. | Beam | 0/10 |
8. | Steel Truss Roof | 0/20 |
9. | Painting | 0/5 |
10. | Finishing | 0/5 |
Total Persentase | 22/100 |
And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :
Front View | Back View |
Right View | Left View |
Another perspective | Another perspective |
Another perspective | Another perspective |
This is the progress report on the construction of the free education center for East Aceh which has started today as of August 20, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.
Official Report WSP : Contruction Progress of Free Education Center East Aceh 5% [August 5, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 12% [August 11, 2022]
Official Report WSP : Contruction Progress of Free Education Center East Aceh 17% [August 16, 2022]
Project | Free Education Center |
---|---|
Type | Buiding Contruction |
Size or Dimention | 9 x 6 meter |
Address | Tanjong Punti village, Madat district, East Aceh |
Benefit recipients | Early Childhood |
Teacher | @steemitcountry |
East Aceh, August 20, 2022
@klen.civil
WSP Construction Supervisor
Your activities are amazingly good activities done 👍
Thanks
very good activity for the community
Thank you so much
Oh wow! You've made a lot of progress since the last report.
Thank you!!
😇
This initiative is wonderful. I commend your effort in this project. Keep it up.
Thanks
Hermoso el trabajo que están realizando.
Mis oraciones con ustedes para que la culminación sea pronto y efectiva.
Thanks
This time you have shown considerable progress since the last post. All the best.
Thanks
Todo va, viento en popa como dicen en mi tierra.
This post has been featured in the latest edition of Steem News...
Thank you