Official Report WSP : Contruction Progress of Free Education Center East Aceh 27% [August 26, 2022]
![]() |
---|
The construction of the free education center for East Aceh, whose funding source is from steem under the auspices of the World Smile Project charity, has now progressed to construction at 27% of the total 10 main work items. Where three main work items have been completed, namely Site Clearing and Landing Altitude Measurement with a weight of 5%, Footing with a weight of 10% and Sloof with a weight of 10%. While one main work item currently being worked on is Post with a weight of 2% out of 15% of the total weight.
At this time the focus of the work items being carried out by workers is completing iron work for posts and making formwork for posts. The slight delay in the construction progress of the free education center for East Aceh this week was due to one worker who was sick along with the weather in East Aceh which became an obstacle in terms of this work, namely this week heavy rain had washed over the area.
However, the target that I do together with the other team is to complete this post work no later than 6 working days in the future, where the addition of workers will be by adjusting work items according to construction engineering management simultaneously. Well, for details on the construction of the free education center, the progress of its construction can be seen in the table and current conditions as below.
No | Type of Work | Persentase |
---|---|---|
1. | Site Clearing and Landing Altitude Measurement | 5/5 |
2. | Footing | 10/10 |
3. | Sloof | 10/10 |
4. | Round Floor Building | 0/8 |
5. | Post | 2/15 |
6. | Wall | 0/12 |
7. | Beam | 0/10 |
8. | Steel Truss Roof | 0/20 |
9. | Painting | 0/5 |
10. | Finishing | 0/5 |
Total Persentase | 27/100 |
And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :
![]() | ![]() |
---|---|
Front View | Back View |
![]() | ![]() |
Right View | Left View |
![]() | ![]() |
Another perspective | Another perspective |
![]() | ![]() |
Another perspective | Another perspective |
![]() | ![]() |
---|---|
Multiplex for formwork | Stone for casting |
![]() | ![]() |
Iron for post | Iron for post |
![]() | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
This is the progress report on the construction of the free education center for East Aceh which has started today as of August 26, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.
East Aceh, August 26, 2022 |
In Venezuela we are also in the rainy season, that delays construction a bit, but everything is going very well with this project.
Again my admiration.
Thank you for the support
You are doing a very good deed! Good luck and success!
Thanks
Hola Klen, lamento los contratiempos que tuvieron, sin embargo veo que están trabajando super fuerte para llevar a término esta obra. 😃✌️
Mis mejores deseos para ustedes.
Hopefully this construction work will be completed quickly
@tipu curate
;)
--
This is a manual curation from the @tipU Curation Project.
Upvoted 👌 (Mana: 0/6) Get profit votes with @tipU :)
Your activity is very good, and the post posts are of very good quality 😁👍
Thank you for your feedback my friend!
It is a pity about the rain but then on the other hand, they wait might be sweeter in the end. (•ิ‿•ิ)
Yes, in the past week, Aceh has been raining