Budget Calculation for Concrete Works In Bridge Project 10 m x4 M
In last week's post, I have explained How To Plan and Analyze Costs Budget of Bridge by size 10 M x 4 M. Read more click here. And in this post will explain what I have not had time to explain in the post last week.
Based on the description I have outlined in last week's post, it is known:
cost required for material Rp 73.899.000 + equipment Rp 4.234.000 + Wage Rp 18.000.000 = Rp 96.133.000 in bridge work 10 M x 4 M.
The budget plan above does not include fees for concrete work. Well, How much does it cost for concrete work on the construction of a 10 M x 4 M bridge?
Hello ....friends steemit it all. to know in calculating the cost of the bridge construction is the volume of work. without we know the volume then we will not be able to calculate the amount of cost required. In last week's post I have done the work volume calculation / Take Of Sheet bridge which I then make in the table.
In this post it is necessary to re-attach the table of volume / TOS calculation in order to facilitate me in preparing the Budget Plan needed for concrete work. TOS is a reference in calculating the required cost.
Volume Calculation/Take Of Sheet
Budget Plan to be spent on bridge concrete work on the bridge construction project by Size 10 M x 4 M
I finish here and on another occasion I will discussing that is important in preparing the budget of the bridge construction cost. [hopefully this is useful for all]
The calculation of development planning budget is very important to be prepared, because it makes it easier for us to design buildings with certain costs.
thank you for commenting on my blog
Are you wellcome....
thanks a lot agian
Harigato...