WSP - Report on the use of funds for Water System and Public Latrine Activities [January 30, 2022]
Starting from January 15, 2022, the construction of the Drinking Water System and MCK which was built from the World Smile Project budget has increased, where the increase is the completion of the foundation or foundation of the building being built.
This is the second phase report on the use of the world smile project funds
The following is an attachment for the use of funds for the third phase of the world smile project in detail:
The planned budget is Rp. 62,000,000 or the equivalent of 967 SBD or 13,285 STEEM. This figure can fluctuate with coin prices that go up and down.
Here, I attach proof of purchase of the manufacturer's materials:
Project Name | Water System and Public Latrine |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Until today, the world smile project cash fund has been used as much as Rp. 19,905,000,- or the equivalent of 310.40 SBD / 4,265 STEEM at today's market price.
For the first stage report, you can directly visit the following post link:
Cc: @pennsif @el-nailul @heriadi @irawandedy @klen.civil @sofian88 @mariana4ve
regards @miftahuddin |
---|
Well detailed report! Thank you for letting us know the progress of this project.
My supports are fully in the project.
All the best
thank you
Laporan yang bagus dam terimakasih atas informasi yang akurat :)
Salam
Do I need to make introduction post for posting in this community?
please continue
You are doing really good work, may you get more success in this deed of helping others
thanks for the support.. #worldsmileproject50pc