World Smile Project : Construction of Free Education Center - Update October 26, 2021

in STEEM FOR BETTERLIFE3 years ago (edited)
Note: 25% of Rewards to accelerate the construction of the Free Education Center through the @worldsmile account

image.png

World Smile Project : Construction of Free Education Center

Of the 12 main jobs from the construction of the free education center, 6 have now been completed, namely Pole or Column, Lower Beam, Floor Adhesive, Floor, Top Beam and Trestle. While the other 2 main jobs, namely Wall and Roof, have done work with a weight of approximately 1/4 of the work. The target for completion of these two works will be completed in a maximum of 1 week.

While other jobs will follow after the 2 jobs above that I mentioned are done perfectly. For the real conditions of the free education center construction and the progress table, I attach as proof of the transparency of this activity. For the development or movement of progress from the construction of the free education center, currently it has reached approximately 1/2 of the total main work in this development

Table of the main types of work from the construction of the Free Education Center
NumberType of workNotes
1Pole or ColumnComplete
2Lower BeamComplete
3Floor AdhesiveComplete
4FloorComplete
5WallAlmost Complete
6Top BeamComplete
7TrestleComplete
8RoofAlmost Complete
9StairsOn Progress
10CeilingOn Progress
11Electrical installationOn Progress
12PaintingOn Progress
Design of the Free Education Center Construction

Progress of Free Education Center Development As of October 26, 2021
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Right Viewimage.png
Left Viewimage.png
JOBS THAT HAVE BEEN WORKED A FEW TIMES AGO
IMG20211025221443.jpgIMG20211025222306.jpg
IMG20211025221503.jpgIMG20211025221443.jpg
IMG20211025211402.jpgIMG20211025221653.jpg
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameFree Education Center
BeneficiaryKhairul Huda School Boarding
AddressSyamtalira Aron, North Aceh - Indonesia

Related Links


Note:


  • Update Construction Progress with Complete Percentage Values ​​can be seen in @sofian88's post (Free Education Center)
  • Completely update budget expenditure can be seen in @miftahuddin's post (Free Education Center)
  • Total Budget Revenue and Expenditure from the World Smile Project is handled by @heriadi and @irawandedy
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @steemcurator01 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 2 years ago 

Thanks a lot.

#club100

 3 years ago 

Que bonito está quedando. Será n lugar donde los niños se sentirán bien. Gracias por tu aporte.

 3 years ago 

Of course this is a job for us to support each other

😇

Mantap bro pembangunan akan segera selesai sukses terus

#club5050
#worldsmileproject50pc

 3 years ago 

Thanks

 3 years ago 

I hope this free educational construction program has been an inspiration to many, I am very proud.

#club5050
#worldsmileproject50pc

 3 years ago 

Thanks

 2 years ago 

Semoga berjalan dengan lancar hingga selesai.

#club5050
#worldsmileproject50pc

 2 years ago 

Tinggal.naik atapya ya..

 2 years ago 

Ya ni kak.
Kemungkinan besar minggu depan atapnya akan selesai

 2 years ago 

Syukurlah cpt jg prosesnya ya.

Such a nice construction, this is really encouraging.
#club5050
#worldsmileproject

Coin Marketplace

STEEM 0.29
TRX 0.12
JST 0.033
BTC 62559.43
ETH 3092.10
USDT 1.00
SBD 3.86