World Smile Project : Construction of Free Education Center - Update October 24, 2021
As of October 24, 2021, the construction of the free education center continues to experience a significant increase. This can be seen from the type of main work that has been done perfectly. In the past few days the workers continued to do their work both during the day and at night, the 12 main jobs that were carried out now the workers have completed and almost complete the 4 jobs, namely Pole or Column, Lower Beam, Floor Adhesive, and Floor.
Currently the workers are continuing the work on the Top Beam and Trestle in different locations, where after the trestle is installed by binding the top gavel together with the top beam, the workers will take it to the construction site and will install it on the pole or also called the main column.
The process is expected to be completed in the next two days, while the roof will be done together with the walls at a later stage. To note, the percentage weight of this development progress has exceeded 1/4 of the construction of the Free Education Center. To make it clearer, I have attached all the details of this main work as shown in the table below, and I also attach a photo-type document which is the current condition of the construction.
Number | Type of work | Notes |
---|---|---|
1 | Pole or Column | Complete |
2 | Lower Beam | Complete |
3 | Floor Adhesive | Almost Complete |
4 | Floor | Almost Complete |
5 | Wall | On Progress |
6 | Top Beam | On Progress |
7 | Trestle | On Progress |
8 | Roof | On Progress |
9 | Stairs | On Progress |
10 | Ceiling | On Progress |
11 | Electrical installation | On Progress |
12 | Painting | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View |
Project Name | Free Education Center |
---|---|
Beneficiary | Khairul Huda School Boarding |
Address | Syamtalira Aron, North Aceh - Indonesia |
Related Links
Note:
- Update Construction Progress with Complete Percentage Values can be seen in @sofian88's post (Free Education Center)
- Completely update budget expenditure can be seen in @miftahuddin's post (Free Education Center)
- Total Budget Revenue and Expenditure from the World Smile Project is handled by @heriadi and @irawandedy
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @steemcurator01 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil
I have included this post in the 15th issue of Steem News Magazine For Steemit Platform | October 25, 2021.
get tuan
Semoga pengerjaan proyek pembangunan gedung pendidikan gratis segera selesai sukses terus
#club5050
#worldsmileproject50pc
great work shown from the world smile project team in helping to build the best educational center
#club5050
#worldsmileproject50pc
Thanks
Semakin keliatan progres dari pengerjaan pembangunan nya, semoga pembangunanya bisa selesai sesuao.rencana ya
#ckub5050
#worldsmileproject50pc
Aamiin
Semoga banyak orang bisa merasakan keberadaan fasilitas gedung ini.
#club5050
#worldsmileproject50pc
Aamiin
It is amazing, I hope that the construction of this free educational center will be completed quickly and can be used to the fullest extent possible, hopefully for the benefit and impact of our communities. I am so proud.
#club5050
#worldsmileproject50pc
Aamin
Beramal sambil kerja
Kerja sambil beramal
#club5050
#worldsmileproject
Semoga cepat selesai dan bisa digunakan segera....
Aamiin
This post has been featured in the latest edition of Steem News...
Thanks a lot
#club5050 😀
Thanks a lot
#club5050
#club100