Greetings, how are you? It's nice to see you again, I'm still going to discuss about issues related to development work, today we will find out how much power and material is needed in the foundation work of a mountain rock foundation.

Rock foundations are usually used in simple buildings such as single-storey houses and so on, the use of this foundation is considered cheaper than other types of foundations, and the ease with which materials are required, but also depends on the strength of the soil.

The initial work that we do is excavation of the ground as the foundation place is put, after the excavation work is completed then the work of the mountain stone foundation pairs can be done.

The equipment required on the excavation work is shovel and hoe, at this stage of work excavation will be done in accordance with the plan.


We will follow the image below either in the excavation, the width of excavation and the length of the excavation to fit the plan that we will do.



We will determine the length of the excavation is 8.00 meters


If the total length of the excavation is 8.00 m, the width of the excavation is 0.60 m and in the excavation is 0.70 m then the total excavated volume to be dug is 2.88 M3, the question is how much power is required in this work process?

I will outline the answer in accordance with the Indonesian National Standard:

At a simple job as deep as a maximum of 1 meter the required energy is, foreman and workers / laborers.
The coefficient of 1 M3 of excavation is:
0.75 Person per Day (Workers)
0.25 Person per Day (Overseer)


Answer:
Volume x coefficient = volume required
2.88 x 0.75 = 2.16 Person per Day (Workers)
2.88 x 0.025 = 0.072 Person per Day (Overseer)
So if we round out the answer is:
To complete the work with a volume of 2.88 M3 required 2.00 workers and 1.00 foreman, the price of wages of workers and foremen per day certainly we can estimate after we take into account the needs of the workforce.


If we have the form of a continuous foundation / stone times as shown below then how many workers need construction workers and how much material is needed



We continue the calculation of the excavation work above, so the length of the foundation stone mountain is 8.00 meters.


Given the size of the mountain rock foundation is:
Top field = 0.25 m
Bottom field = 0.60 m
Height = 0.70 m
Length = 8.00 m
Then the total volume of the foundation is (((top width + bottom width) / 2) x 0.700 x 8,000 = 2,380 M3
In accordance with the Indonesian National Standard on the work of pindasi stone with a mixture of 1 portland cement: 4 sand is.

  • 1,500 Person per Day (Workers)
  • 0.750 Person per Day (Stonemason)
  • 0.0750 Person per Day (Foreman)
  • 0.0750 Person per Day (Overseer)
  • 1,200 M3 Stone Mountain
  • 163,000 Kg Portland Cement
  • 0.520 M3 Sand pairs

Answer:
Volume x coefficient = volume required
2,280 x 1,500 = 3,570 Person per Day (Workers)
2,280 x 0.750 = 1,785 Person per Day (Stonemason)
2,280 x 0.075 = 0.1785 Person per Day (Foreman)
2,280 x 0.075 = 0.1785 Person per Day (Overseer)
2,280 x 1,200 = 2,856 M3 Stone Mountain
2,280 x 163,000 = 387,940 Kg Portland Cement
2,280 x 0,520 = 1,2376 M3 Sand pair


So if we round out the answer is:
To complete the foundation work with a volume of 2,380 M3 it takes 4,00 workers, 2,00 stonemason and 1.00 Foreman as well as Overseer, while the required building materials is 3,00 M3 Stone Mountain, 389,00 Kg Portland Cement and 1.50 M3 Sand pair.

If all the needs of labor and building materials have been known then the next stage is to determine the price of each item.


CONCLUSION


The need for manpower and building materials to complete the excavation work with a volume of 2,880 M3 and a mountain rock foundation with a volume of 2,380 M3 is :

ItemsVolume requirement
Worker6.00 Person
Stonemason2,00 Person
Foreman or Overseer1 Person
Stone Mountain3 M3
Portland Cement389.00 Kg
Sand pair1.50 M3

In this calculation I only put on the foundation work, hopefully with this paper can help the young engineers in understanding the volume of needs in other areas of work.



A photo of a mountain rock foundation on the construction work I ( @kharrazi ) did a few years ago


This is all I can write now, for all the errors of writing and as a servant of God I apologize.
Thanks to all my friends who have visited the blog and to friends who have constructive comments.


source:

en.wikipedia.org Foundation (engineering)

id.wikipedia.org Teknik fondasi

www.hdesignideas.com

en.wikipedia.org Technical analysis


Do you love science? then join us at steemstem using @science tags and @steemstem, you can also chat with us at steemstem chat. channel.


Best regards @kharrazi

Sort:  

I might have missed it in the post, but where is this construction taking place in the photos? Do you regularly work on this tomorrow of project?

Aceh, yup. but this project has been finished a mount a go. Thanks for stoping my friend @hartsuff1

Wow @kharrazi your article was quite high in information and knowledge I sometimes feel steemit is making people share their thoughts and keep their point of view. I quitely rate your post and more 2-3 authors as best authors who share best articles.
@originalworks must check your post and upvote your great article.

The @OriginalWorks bot has determined this post by @kharrazi to be original material and upvoted it!

ezgif.com-resize.gif

To call @OriginalWorks, simply reply to any post with @originalworks or !originalworks in your message!

To nominate this post for the daily RESTEEM contest, upvote this comment! The user with the most upvotes on their @OriginalWorks comment will win!

For more information, Click Here!

thank you my friend @sid9999, I'm glad you like it.

Reblogged — let’s promote quality content!

Congratulations @kharrazi! You have completed some achievement on Steemit and have been rewarded with new badge(s) :

You published a post every day of the week

Click on any badge to view your own Board of Honor on SteemitBoard.
For more information about SteemitBoard, click here

If you no longer want to receive notifications, reply to this comment with the word STOP

By upvoting this notification, you can help all Steemit users. Learn how here!

Coin Marketplace

STEEM 0.20
TRX 0.15
JST 0.030
BTC 65847.68
ETH 2679.11
USDT 1.00
SBD 3.08