WSP - Report on the use of funds for Water System and Public Latrine Activities [February 01, 2022]
Starting from January 15, 2022, the construction of the Drinking Water System and MCK which was built from the World Smile Project budget has increased, where the increase is the completion of the foundation or foundation of the building being built.
This is the second phase report on the use of the world smile project funds
The following is an attachment for the use of funds for the third phase of the world smile project in detail:
The planned budget is Rp. 62,000,000 or the equivalent of 1.041 SBD or 13,641 STEEM. This figure can fluctuate with coin prices that go up and down.
Here, I attach proof of purchase of the manufacturer's materials:
| Project Name | Water System and Public Latrine |
|---|---|
| Beneficiary | Kumbang Village Community |
| Address | Syamtalira Aron, North Aceh - Indonesia |
| Map | what3words.com |
Until today, the world smile project cash fund has been used as much as Rp. 29.885.000,- or the equivalent of 489.40 SBD / 6,575 STEEM at today's market price.
For the first stage report, you can directly visit the following post link:
WSP - Report on the use of funds for Water System and Public Latrine Activities [January 30, 2022]
WSP - Report on the use of funds for Water System and Public Latrine Activities [January 26, 2022]
WSP - Report on the use of funds for Water System and Public Latrine Activities [January 24, 2022]
WSP - Report on the use of funds for Water System and Public Latrine Activities
Cc: @pennsif @el-nailul @heriadi @irawandedy @klen.civil @sofian88 @mariana4ve
| regards @miftahuddin |
|---|






Getting a well detailed positive report is exciting and at the same time encouraging. We'll keep doing our best by supporting to make sure that this project is successful.