Some previously unidentified stakeholders report that they have not beenkept informed regarding the status of a critical project even thought their functional areas are largely impacteWhat should the project manager dofirst?
A. new strategy for to despanine the status of communication projects.
B. Invites all stakeholders to the State meetings.
C. review project communication methods.
D. check and update the stakeholders register.

一些之前未识别到的相关方报告说,他们的职能领域受到很大影响,但没有持续通知他们关键项目的状态。项目经理首先应该做什么?

A. 确定沟通项目状态的新策略
B. 邀请所有相关方参加状态会议
C. 审查项目的沟通方法
D. 检查并更新相关方登记册


6.11 期答案:C
解析:一位关键职能经理提出多项项目变更,首先需要分析这些变更是否都有必要进行,所以要先向相关方咨询建议的变更。
所属过程组:监控过程组
知识领域:项目整合管理