Official Report WSP : Contruction Progress of Free Education Center East Aceh 75% [September 25, 2022]
Until 5:05 pm Western Indonesia time, on September 25, 2022, I was still at the construction site of the free education center in East Aceh and at this time the roof installation process is continuing for this construction. Of the 9 main items from the work of the free education center, now only a few main items are being worked on. And for today the main work focus in the form of roof installation has reached 75% completed with a weight of 15% of the total 20% of this work item.
The target for the completion of this roof in the next half day, apart from the roofing work item, the completion of the brickwork in this free education area together with plastering is the focus of me and the workers in completing this construction. For floor work items will be carried out simultaneously with painting the wall area when the wall item has been completed.
From all work items that have been done, are being worked on, and have not been done, it can be concluded that the free education center for East Aceh, whose funding source comes from the steemit platform through the World Smile Project Int container, can be stated to have had construction progress of 75% of the total. In detail, the construction progress and conditions of the free education center are attached below for WSP donors to see.
No | Type of Work | Persentase |
---|---|---|
1. | Site Clearing and Landing Altitude Measurement | 5/5 |
2. | Footing | 10/10 |
3. | Sloof | 10/10 |
4. | Round Floor Building | 3/8 |
5. | Post | 15/15 |
6. | Wall | 7/15 |
7. | Beam | 10/12 |
8. | Steel Truss Roof | 15/20 |
9. | Painting | 0/5 |
Total Persentase | 75/100 |
And below I also attach several documents in the form of photos of the work carried out today, as follows :
Front View | Back View |
Right View | Left View |
Another perspective | Another perspective |
Another perspective | Another perspective |
Another perspective | Another perspective |
Another perspective | Another perspective |
This is the progress report on the construction of the free education center for East Aceh which has started today as of September 25, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.
Project | Free Education Center |
---|---|
Type | Buiding Contruction |
Size or Dimention | 9 x 6 meter |
Address | Tanjong Punti village, Madat district, East Aceh |
Benefit recipients | Early Childhood |
Teacher | @steemitcountry |
East Aceh, September 25, 2022
@klen.civil
WSP Construction Supervisor
Hello friend!
I'm @steem.history, who is steem witness.
Thank you for witnessvoting for me.
please click it!
(Go to https://steemit.com/~witnesses and type fbslo at the bottom of the page)
Great progress this week my friend! Thank you to you and the team. 👍
It is hard to believe how you guys made progress with that roof today.
The end is in sight. Keep on sharing!