Finishing Forms, Pouring and Removing Forms - August 22, 2019 @goldenoakfarm

Construction - still not built1 crop August 2019.jpg
August 20th, still not built #1

Construction - still not built2 crop August 2019.jpg
August 20th, still not built #2

Construction - still not built3 crop August 2019.jpg
August 20th, still not built #3

Construction - new sump area crop August 2019.jpg
The new sump area, straight down

Construction - 1st truck of last pour crop August 2019.jpg
August 21st, 7AM, the first truck of concrete arrives

Construction -  pouring bulkhead crop August 2019.jpg
Pouring the bulkhead

Construction -  curing walls1 crop August 2019.jpg
The pour finished, the walls curing #1

Construction -  curing walls2 crop August 2019.jpg
The pour finished, the walls curing #2, the short wall

Construction -  curing walls3 crop August 2019.jpg
The pour finished, the walls curing #3, with sill bolts

Construction -  extended masonry heater pad crop August 2019.jpg
The extended masonry heater pad

Construction -  curing walls4 crop August 2019.jpg
The pour finished, the walls curing #4 – the bulkhead

Construction - walls revealed1 crop August 2019.jpg
The forms come off on the inside #1

Construction - walls revealed2 crop August 2019.jpg
The forms come off on the inside #2

They should be finished up tomorrow. The walls will be cured enough by the weekend. I will be “Tar-Baby” as I will be putting the foundation sealer on, probably wearing as much as the walls…

Join Us on Discord. https://discord.gg/hPJs5Rb

Sort:  

Is this an additon to your homestead?
I see a home in the photos.

Yes, we are going to 1 floor living, as we are getting old... :))

Coin Marketplace

STEEM 0.19
TRX 0.15
JST 0.029
BTC 62956.16
ETH 2588.54
USDT 1.00
SBD 2.74