『单选题』
A project manager has an agreement with a third-party supplier to deliver parts within six months. During the implementation phase, the project is cancelled . However, the supplier has already started work on this order.
What should the project manager do next?
A. Review the contract's spanination clause.
B. Conduct a supplier performance evaluation.
C. Direct the supplier to stop work immediately.
D. Update the procurement managerment plan.

项目经理与第三方供应商签订在六个月内交付零件的协议,项目在实施阶段被取消了。但是,供应商已经开始这个订单的工作了。项目经理下一步应该怎么做?

A 审查合同终止条款
B 进行供应商绩效评估
C 指示供应商立即停止工作
D 更新采购管理计划


5.23期答案为:D
解析:项目必须在短时间内交付,为了提高成功率,需要项目团队在规划阶段就参与进来,项目经理可以选择与团队一起制定详细计划。
所属过程组:规划过程组;
知识领域:项目整合管理