SegWit2x working group calendar
May 23 - Kickoff
May 30 - Pre-Alpha
- More detailed plan sent out to the agreement Participants for feedback
June 16 - Alpha Milestone
- Alpha software ready
- New testnet network setup
- BIP published
June 30 - Beta Milestone
- All comments / issues from Alpha have been addressed
- Testing complete
July 14 - Agreement Participants Install and Test Milestone
July 21 - Nodes Running & Signaling begins