Construction Progress Report from Water System and Public Latrine

Today is January 22, 2022, Of the 11 main works on the construction of the Water System and Public Latrine, three works have been completed and two are in progress. Three jobs that have been completed are Bouwplank, Footing and Sloof. While the two works being carried out are Column, Wall and Water tub, where the main column work for all the steel has been installed and the other has been wrapped with formwork which has been filled with concrete.

For the walls of the building that have been installed in the latrine section and are almost finished, the steps to be carried out on the walls are to complete the brickwork and at the same time install pipes on the wall as a place for installing water faucets, while other work that is deemed necessary is a water tub, this work has reached less than half the work.

The three works that are being carried out by these workers will be completed within the next day at the latest, in addition, after this work is completed, the next step is to install the beams, plaster and install wall tiles. The floor work will also be carried out in conjunction with the completion of the water tub in this building.

For analysis of construction techniques from the Water System and Public Latrine per day it has reached 24% this happens because the work items are 11 and can be categorized by separating each work item itself. For more details, you can see as in the table and the current condition of each work on the construction as below.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnAlmost complete
5.WallAlmost complete
6.BeamOn Progres
7.FloorOn Progress
8.Water tubAlmost complete
9.RoofOn Progress
10.PaintingOn Progress
11.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front View20220122_173147.jpg
Front and Right View20220122_173200.jpg
Front and Left View20220122_173438.jpg
Right View20220122_173217.jpg
Left View20220122_173323.jpg
Back View20220122_173250.jpg
Back and Right View20220122_173230.jpg
Left and Right View20220122_173308.jpg

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 2 years ago 

Great report.good job

 2 years ago 

Thanks sist

 2 years ago 

Anytime..

 2 years ago (edited)

@klen.civil, te he buscado por Discord y no te consigo. Quisiera saber si tienes grupo para la nueva propuesta de Steemit Blog.

Mi Discord es #0466

 2 years ago 

You can send a message to my telegram, link is in my bio

 2 years ago 

Thank you for updating us on the progress.

This post has been featured in the latest edition of Steem News...

 2 years ago 

Thanks for the information about the progress of the project,
I'm going to write today's article again #worldsmileproject50pc for support. And thank you for giving us the opportunity to do such a charitable thing. 😇🙏🤲

 2 years ago 

I have included this post in the 31th issue of Steem News Magazine For Steemit Platform | January 22, 2022.

 2 years ago 

almost on its half way dear... Keep it up...

 2 years ago 

100.0% уникальности текста (uniqueness of the text)
Здравствуйте. Это полуавтоматическая проверка уникальности сервисом content-watch. Пожалуйста, сообщайте о неточностях. Уникальность вашей статьи согласно сервиса content-watch.ru равна: 100.0%

Hello. This is a half-automatic uniqueness check by the content-watch service Please report any inaccuracies The uniqueness of your stat th according to the content-watch.ru service is equal to: 100.0%

Coin Marketplace

STEEM 0.29
TRX 0.12
JST 0.033
BTC 63457.41
ETH 3119.12
USDT 1.00
SBD 3.94